24 June 2024
33kV UGC and Fibre Cabling works for the Longman Substation Project being delivered by McGowan Infrastructure have now successfully reached the 1000-metre mark - representing 40% of the total project. This significant progress is a testament to our team's dedication and precision.
Nothing is more important than the safety of our team and our investment in an excavator-mounted Suction Excavator from tinbin TC2 has been crucial in ensuring the highest safety standards while working around live services.
Simultaneously, our efforts on the 33/11kV Substation construction are progressing smoothly. We have successfully removed and rerouted the live cables within the platform, completed the site clearance, and are well underway with the reinforced concrete works.
Here's to more milestones and continued success!